Task Start and End Date Duration Calculation

One feature to assist in calculating task duration appears only when input is made to both a start and end date. It is used to calculate the duration so that a "Must Start on Constraint" is set with a duration which equals the desired end date.

Note that this will not set an end date, as the end date remains dynamic based on the duration and other scheduling factors such as assigned resource personal schedules. If you need the end date set, then the task will need to be edited to have a "Must Finish On:" contraint as opposed to a "Must Start On" constraint type.